The problem of construction of small or relatively medium waste incineration plants is presented in the present work with the aim to stimulate discussion as to what types of incineration plants should be constructed. What the advantages and disadvantages of small (a few thousand tons of waste per year), medium (over a dozen thousand tons of waste per year), and large (from a few dozen up to 150 thousand Mg/year) incineration plants are.

The capacity (incinerator feed) of the waste incineration plant designed for the Połczyn Zdrój municipality is only about 3700 Mg/year.

The research and design analysis performed in the present work show that:

Słowa kluczowe
spalarnia odpadów, projekt koncepcyjny, analiza ekonomiczna

Conceptual Project of Construction of Waste Incineration Plant for Połczyn Zdrój Municipality

Keywords
waste incineration plant, conceptual project, economic analysis